River Road Interceptor

The River Road Interceptor was constructed as a part of an Agreed Order with the State of Kentucky and led to the elimination of five package treatment plants. The project included 4300 feet of 36-inch sewer, 1500 feet of 42-inch sewer and a parallel force main. The 42-inch sewer was up to 40 feet deep in some locations and included two crossings under Harrods Creek, a major navigable waterway as well as a crossing under State Highway 42. The 36-inch sewer included two road crossings and nine small creek crossings. The project also included easement acquisition across 22 properties.

Project Details

CLIENT

Louisville Metropolitan Sewer District

Location

Louisville, KY

Services Provided
  • Easement plat preparation
  • Sewer Design
  • Oversight of environmental process
  • Permitting
  • Utility Coordination
  • Design Services
  • Survey
  • Route Selection
  • Bidding document and assistance